However the site was excavated yesterday for landscape but the tilers today again had some wastes dumped on the soon-to-be lawn areas. Don't know if the landscape people are going to be happy or not when they find out.
Also since tiling was meant to be done last week we had to turn away followings today because they didn't have access. They all need to be re-scheduled and they will affect other things too, such as cleaning, which will need to be re scheduled too.
- Carpenters for the wardrobe shelves fit out
- Blinds installation, and
- most importantly, the timber floors!
Quite a bit of knock-on effects! It looks like sometimes you need to be on someone's back all the time to make sure they did what they were meant to do! Tilers actually did all right (in terms of progress). It's just that someone forgot to tell them to start until I actually found out myself a few days before handover!