Detailed Timeline

Last Updated: 29 Mar 2011 (Week 62)

Note: Construction time excluding 5 weeks:
Week 44 - 45: Idle
Week 49 - 51: X'mas break
No. of
Weeks   Activity
===========================================
20  Construction
    2  Handover
    2  Electrical
    2  Tiles, Wet area
    1  Painting done
    1  Doors fitted, lockec up
    1  Gyprock
    1  Insulation
    1  A/C and Electrical
    3  bricks completed
    2  frame completed
    2  Slab, plumbing pipes completed
    2  Issuing Work order and ordering materials
-------------------------------------------
22  Authorities' approval (5 mths)
    3  Construction certificate issued
    7  Development Application, including
       2 weeks: returning documents
       2 weeks: determination
       2 weeks: public exhibition
       1 week: lodgement
    12 developer approval
       8 weeks extra due to:
       2 weeks: 2nd review
       1 week:  acquire new BASIX
       3 weeks: amending drawings
       2 weeks: submission delay
-------------------------------------------
11  Pre Submission (2.5 mths)
    5  Design
       4 weeks: Landscape design
       1 week: Colour selection
    6  Contract preparation
       2 weeks: Contract completed and signed
       4 weeks: Tender prepared
===========================================
53    Weeks - Total

A more graphical view is here - click to open a new window for larger view. In this table delays that could have been avoided are shown in red.

There are also four colours to show four different processes, acquiring land, organising finance, house and landscape.