Saturday, September 11, 2010

Something for nothing?


Went to site this afternoon and found out someone 'left' a small pile of pebbles on my block - there is no construction on my neighbour blocks. It might be from the house opposite the street?

Not much else to report as we still haven't got the construction certificate. The approval seems to take forever - so far it's taken:
  • 12 weeks to go through Ponds Review Board;
  • 7 weeks to get the Development Application through council; and
  • 2 weeks into getting Construction Certificate (CC)
That is almost 5 months and still counting! It may still take another 1 - 2 weeks for CC to be issued and then builder needs to issue their work orders, construction drawings and order materials. So the actual site start seems to be 4 - 6 weeks away!

Hopefully the builder will get the paperworks done soon so that they can fence off the block and it won't become nearby builders dumping ground!