Sunday, December 19, 2010

Week 47 - We've got insulation, AKA pink bags

I didn't expect to see there progress prior today's visit as I thought many tradies would have been in the industry standard 5-week Christmas shutdown. However I did see the insulation is being put on but not quite completed yet. Not sure if they will finish it next week.

Even so these are what were done in the past 4 weeks:
  • Week 44: nothing
  • Week 45: bricks cleaned
  • Week 46: air conditioning ducts and electrical
  • Week 47: insulation partially done
That was not terribly a lot I have to say. It's probably 1 week worth of work really. We'll just have to wait and see how they go once they come back from Christmas break. Fingers crossed!